Day 15
Day 15
Day 15
Day 15
September 22nd, 2010 Wednesday
Day 15 - Crew making good progress, stacking logs. Trash Dumpster delivered and jobsite cleaned.
September 23rd, 2010 Thursday
Day 16 - Crew close to having log wall stack complete. Well contractor onsite, drilled approximately 170 feet deep and installed 1.5 hp pump with tank.
Day 16
Day 16
Day 16
Day 16
Day 16
September 24th, 2010 Friday
Day 17 - Crew continues log wall stack, installs decking on 12ft back covered porch. Built temporary stairs. Received interior framing package. Electric company onsite, set transformer and energized temporary electric pole.
Day 17
September 25th, 2010 Saturday
Day 18 - Crew continues working on log stack.

September 26th, 2010 Sunday
Day 19 - No Work

September 27th, 2010 Monday
Day 20 -  Rained out.

September 28th, 2010 Tuesday
Day 21 -  Log walls complete, Interior Framing 50%.
Day 18
Day 21
Day 21
September 29th, 2010 Wednesday
Day 22 - Worked 1/2 day due to rain. Crew continues working on framing and starts roof support post.

September 30th, 2010 Thursday
Day 23 - Crew works on Structural Open Beam Roof System
Day 23
Day 23
Day 23
October 1st, 2010 Friday
Day 24 - Crew working on open beam roof system.

October 2nd, 2010 Saturday
Day 25 - Crew installed all rafters on Structural Open Beam Roof System
October 3rd, 2010 Sunday
Day 26 -  No work.

October 4th, 2010 Monday
Day 27 - Crew working on full log gables ends.

October 5th, 2010 Tuesday
Day 28 - Crew finished full log gables.
Day 25
Day 28
Day 28
Day 28
October 6th, 2010 Wednesday
Day 29 - Crew begins installing T&G roof covering. Electrician onsite coordinating wiring drops for ceiling areas and scheduled to be onsite to install on Monday.
Day 29
Day 29
October 7th, 2010 Thursday
Day 30 - Crew finishes installing T&G roof covering.
October 8th, 2010 Friday
Day 31 - Crew  working on installing open beam roof purlin system.
October 9th, 2010 Saturday
Day 32 - Crew finishing open beam roof purlin system and working on open beam covered porches.

October 10th, 2010 Sunday - Day 33 - No work.
Day 30
Day 31
Day 31
Day 32