December 1st, 2010 Wednesday
Day 84 - Finish carpenters onsite installing interior window/door trim, wainscot and chair rails. Tile crew onsite. Glass contractor onsite getting measurements to fabricate shower door. Cabinet makers onsite installing hardware; cabinets 100%.
Health Department Inspector onsite; completed septic inspection and signed off.
December 2st, 2010 Thursday
Day 85 - Finish carpenters onsite installing interior doors and trimout. Tile crew onsite. Visited Building Dept. and paid year end tax's to release power. Stone crew back onsite; owners ok' d changeorder to wrap foundation and piers with stone.
December 3rd, 2010 Friday
Day 86 - Power Company onsite; House energized under live power. Finish carpenters onsite installing interior doors and trimout of bay window. Electricians onsite working on trimout and checking out equipment. HVAC contractor onsite; energized system and tested, system 100%. Countertop contractors onsite; installed granite 100%. Stone crew continuing to work on wrapping foundation. House under heat, ran at 85 degrees overnight to 72 degrees in daytime hours.
December 4th, 2010 Saturday
Day 87 - Finish carpenters onsite working on trimout. Stone crew continuing to work on wrapping foundation. Tile contractor onsite.
December 5th, 2010 Sunday
Day 88 - Stone crew finished wrapping foundation and piers. Tile contractor onsite.
December 6th, 2010 Monday
Day 89 - Finish carpenters onsite working on trimout. Stone crew cleaning up and leaving job, 100% complete. Plumbers onsite; working on trimout (setting toilets, sinks, faucets etc.) Also set exterior water filtration system.
December 7th, 2010 Tuesday
Day 90 - Finish carpenters onsite. Plumbers onsite; working on trimout. Australian Cypress hardwood flooring delivered, opened all box's and will let acclimate for five days before installation. Insulation Contractors onsite; sprayed Icynene under complete floor system, 100% complete.